Ghost Orchid Solar Energy Center

Hendry County, Florida · EIA plant ID 65038 · Operator: Florida Power & Light Co
SolarSolar PhotovoltaicBA: FPL
Nameplate75MWSummer 75 MW
Generators1in service
Net generation146GWh12 mo to Aug 2026
Capacity factor22%solar units, summer MW
Heat rate—thermal plants only
First online2022

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
051015GWh20222023202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%20222023202420252026202722.4% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2022149.322.9%—
2023145.722.3%—
2024145.822.3%—
2025151.723.2%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Solar PhotovoltaicPV74.574.5Jan 2022Operating—coming soon

Owner / operator

Operator: Florida Power & Light Co. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Florida Power & Light Co100.0%75 MW

Nearby plants

Within 80 km.
Hendry—0.8 km
Woodyard75 MW1.6 km
Sawgrass Solar Energy Center75 MW4.4 km
Beautyberry75 MW6.4 km
Blue Heron Solar75 MW33 km