← Back to map

Oxbow Solar 1

Pointe Coupee County, Louisiana · EIA plant ID 65030 · Operator: Lightsource Renewable Energy Asset Management, LLC
SolarSolar PhotovoltaicMISOBA: MISO
Nameplate300MWSummer 300 MW
Generators1in service
Net generation502GWh12 mo to Aug 2026
Capacity factor19%solar units, summer MW
Heat rate—thermal plants only
First online2024

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0204060GWh20252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%202420252026202719.1% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2024301.322.7%—
2025556.421.2%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
LAVE1Solar PhotovoltaicPV300300Jul 2024Operating—coming soon

Owner / operator

Operator: Lightsource Renewable Energy Asset Management, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Oxbow Solar Farm 1, LLC100.0%300 MW

Nearby plants

Within 80 km.
Big Cajun 1493 MW3.5 km
Big Cajun 21,903 MW6.8 km
New Roads9 MW6.9 km
Pointe Coupee Power Station—8 km
St Francisville Mill13 MW8.1 km
Georgia-Pacific Port Hudsonretired10.8 km