Brighter Future SolarRetirement planned

Caldwell County, North Carolina · EIA plant ID 64910 · Operator: brighter future solar llc
SolarSolar PhotovoltaicBA: DUK
Nameplate11MWSummer 11 MW
Generators1in service
Net generation21GWh12 mo to Dec 2025
Capacity factor22%solar units, summer MW
Heat rate—thermal plants only
First online2022Retirement planned Jan 2052

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
00.511.52GWh2022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%2022202320242025202621.6% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
202221.722.5%—
202321.222.0%—
202416.817.3%—
202520.821.6%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
BFSNCSolar PhotovoltaicPV1111Jan 2022Operating · retirement plannedJan 2052coming soon

Owner / operator

Operator: brighter future solar llc. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
brighter future solar llc100.0%11 MW

Nearby plants

Within 80 km.
Granite Falls Walmart2 MW4.3 km
Rhodhiss26 MW7.6 km
Dragstrip Farm5 MW7.6 km
Cline Solar Farm, LLC5 MW11.4 km
Innovative Solar 26, LLC2 MW12.4 km
Flash Solar5 MW14.4 km