← Back to map

Fountain Folkston

Charlton County, Georgia · EIA plant ID 64584 · Operator: Westbound Solar LLC
SolarSolar PhotovoltaicBA: SOCO
Nameplate2MWSummer 2 MW
Generators1in service
Net generation4GWh12 mo to Dec 2025
Capacity factor21%solar units, summer MW
Heat rate—thermal plants only
First online2019

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0200400MWh202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%202020212022202320242025202621.3% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20204.423.9%—
20214.122.1%—
20224.223.1%—
20234.423.9%—
20244.323.1%—
20253.921.3%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
GPFTFSolar PhotovoltaicPV2.12.1Nov 2019Operating—coming soon

Owner / operator

Operator: Westbound Solar LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Westbound Solar LLC100.0%2 MW

Nearby plants

Within 80 km.
Kings Bay Solar Facility30 MW40 km
Naval Submarine Base Kings Bay30 MW43 km
Thomas Creek75 MW44.6 km
Nassau Solar Center75 MW46.4 km
Ware Avra I3 MW46.5 km
Ware Avra II2 MW46.5 km