← Back to map

Valencia 3

Imperial County, California · EIA plant ID 64441 · Operator: Greenbacker Renewable Energy Corporation
SolarSolar PhotovoltaicBA: IID
Nameplate3MWSummer 3 MW
Generators1in service
Net generation4GWh12 mo to Dec 2025
Capacity factor16%solar units, summer MW
Heat rate—thermal plants only
First online2021

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0200400600800MWh2022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%20212022202320242025202616.2% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20215.628.0%—
20228.632.8%—
20238.331.4%—
20246.625.2%—
20254.216.2%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
266Solar PhotovoltaicPV33Apr 2021Operating—coming soon

Owner / operator

Operator: Greenbacker Renewable Energy Corporation. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Greenbacker Renewable Energy Corporation100.0%3 MW

Nearby plants

Within 80 km.
Mesquite Lake Energy Park Plant 221 MW3.1 km
Mesquite Lake Water & Power Plant 1retired3.2 km
CE&P Imperial Valley 1—3.5 km
Spreckels Sugar Company9 MW4 km
IVC Solar3 MW6.6 km