← Back to map

Gold Meadow Farms

Kent County, Rhode Island · EIA plant ID 64108 · Operator: Captona Lippitt Ave Cranston LLC
SolarSolar PhotovoltaicISONEBA: ISNE
Nameplate16MWSummer 16 MW
Generators1in service
Net generation27GWh12 mo to Dec 2025
Capacity factor19%solar units, summer MW
Heat rate—thermal plants only
First online2019

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0123GWh202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%202020212022202320242025202619.1% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
202029.320.6%—
202127.919.7%—
202229.420.7%—
202327.519.4%—
20242819.7%—
202527.119.1%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
CPRI7Solar PhotovoltaicPV16.216.2May 2019Operating—coming soon

Owner / operator

Operator: Captona Lippitt Ave Cranston LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Captona Partners Solar I Finco LLC100.0%16 MW

Nearby plants

Within 80 km.
Hope Farm Solar, LLC10 MW1.5 km
ISM Solar Cranston CSG3 MW5.4 km
Central Power Plant11 MW5.9 km
WED Plainfield III, LLC3 MW6.5 km
Kilvert5 MW6.6 km
WED Plainfield II, LLC3 MW6.7 km