Great Bear Solar, LLCPlanned
Van Wert County, Ohio · EIA plant ID 64073 · Operator: Avangrid Renewables Inc
46 MW planned (Solar Photovoltaic), first expected Dec 2027 · EIA-860M
Nameplate—MWSummer — MW
Generators0in service
Net generation—GWh12 mo
Capacity factor—no 923 generation in the last 12 months
Heat rate—thermal plants only
First online—
Capacity factor by year
Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| GBS | Solar Photovoltaic | PV | 46 | 46 | planned Dec 2027 | Planned | — | coming soon |
Owner / operator
Operator: Avangrid Renewables Inc. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Nearby plants
Within 80 km.
| Blue Creek Wind Project | 302 MW | 2 km |
| Cooper Farms VW Project | 5 MW | 3.9 km |
| Haviland Plastic Products | 5 MW | 8.5 km |
| Northwest Ohio Wind | 110 MW | 8.6 km |
| Grover Hill Wind, LLC | 140 MW | 13.1 km |
| Robert P Mone Plant | 597 MW | 13.2 km |