← Back to map

Lily Solar Hybrid

Kaufman County, Texas · EIA plant ID 63892 · Operator: Lily Solar, LLC
SolarBatteriesSolar PhotovoltaicERCOTBA: ERCO
Nameplate202MWSummer 196 MW
Generators2in service
Net generation319GWh12 mo to Aug 2026
Capacity factor25%solar units, summer MW
Heat rate—thermal plants only
First online2021

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
010203040GWh20222023202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%60%202120222023202420252026202725.2% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2021194.460.2%—
2022368.128.8%—
2023335.326.2%—
2024308.824.3%—
2025318.425.1%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
LILYSolar PhotovoltaicPV146.7146Oct 2021Operating—coming soon
LILYBBatteriesBA55.250Oct 2021Operating—coming soon

Owner / operator

Operator: Lily Solar, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Lily Solar, LLC100.0%202 MW

Nearby plants

Within 80 km.
Anole Energy Storage240 MW10.6 km
Kaufman Solar200 MW19.5 km
Ameresco Dallas LLC4 MW23.9 km
Forney Energy Center1,894 MW25.5 km
Wensowitch Solar Park—26.5 km
TX Sunnyvale 367 Long Creek Road Solar2 MW29.8 km