← Back to map

Ocracoke Hybrid

Hyde County, North Carolina · EIA plant ID 6377 · Operator: North Carolina El Member Corp
OilBatteriesPetroleum LiquidsPJMBA: PJM
Nameplate4MWSummer 4 MW
Generators2in service
Net generation-0GWh12 mo to Dec 2025
Capacity factor0%gas/coal/oil units, summer MW
Heat rate29,643Btu/kWhfossil units, electric fuel, HHV
First online1991Runs as rarely runs

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
-50-250255075MWh20042006200820102012201420162018202020222024

Capacity factor by year

Net MWh ÷ (summer MW × hours), gas/coal/oil units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%1%1%200520102015202020250.2% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
010,00020,00030,0002005201020152020202529,643 Btu/kWh · 12 mo
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2004-0-0.1%—
20050.31.1%19,196
20060.20.7%22,871
20070.31.2%17,138
200800.1%—
2009-0.1-0.3%—
20100.20.8%17,329
20110.20.6%20,961
2012-0-0.1%—
201300.1%—
20140.10.4%24,192
20150.10.3%28,403
2016-0.1-0.2%—
20170.10.5%—
20180.10.5%10,127
20190.10.5%17,191
2020-0-0.1%—
2021-0-0.1%—
20220.10.6%16,399
2023-0.1-0.3%—
2024-0.2-0.3%—
2025-0.10.2%29,643

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Petroleum LiquidsIC33Apr 1991Operating—coming soon
BATBatteriesBA11Jan 2017Operating—coming soon

Owner / operator

Operator: North Carolina El Member Corp. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
North Carolina El Member Corp100.0%4 MW

Nearby plants

Within 80 km.
Buxton15 MW44.1 km
Bayboro Solar Farm5 MW75.7 km
Coogee Solar5 MW76.9 km
Rose Acre Solar Energy Storage5 MW77.4 km
PCS Phosphate54 MW78.5 km