← Back to map

Strider Solar, LLC

Randolph County, North Carolina · EIA plant ID 63270 · Operator: Alchemy Renewable Energy
SolarSolar PhotovoltaicBA: DUK
Nameplate5MWSummer 5 MW
Generators1in service
Net generation9GWh12 mo to Dec 2025
Capacity factor20%solar units, summer MW
Heat rate—thermal plants only
First online2018

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
00.250.50.751GWh2019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%2019202020212022202320242025202620.0% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20199.521.7%—
20208.419.2%—
20219.321.3%—
20228.619.6%—
2023920.6%—
20248.419.2%—
20258.820.0%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
NCSTRSolar PhotovoltaicPV55Apr 2018Operating—coming soon

Owner / operator

Operator: Alchemy Renewable Energy. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Alchemy Renewable Energy100.0%5 MW

Nearby plants

Within 80 km.
Little River PV 15 MW6.9 km
Morning View2 MW7.3 km
Seagrove5 MW7.5 km
Hopewell Friends1 MW8.1 km
Five Points BESS5 MW10.4 km
Old Cedar Solar Energy Storage2 MW12.6 km