← Back to map

Outer Cape Community Battery

Barnstable County, Massachusetts · EIA plant ID 62604 · Operator: Eversource
BatteryBatteriesISONEBA: ISNE
Nameplate25MWSummer 25 MW
Generators1in service
Net generation-0GWh12 mo to Aug 2026
Capacity factor—not meaningful for storage
Heat rate—thermal plants only
First online2022

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
-80-60-40-200MWh2023202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2022-0.1——
2023-0——
2024-0.1——
2025-0.1——

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
OCESSBatteriesBA2525Dec 2022Operating—coming soon

Owner / operator

Operator: Eversource. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Eversource100.0%25 MW

Nearby plants

Within 80 km.
Brewster Landfill1 MW35.8 km
Lepomis PV Energy LLC5 MW37.6 km
CVEC Round 4 Brewster Captn Golf Course1 MW39.3 km
Camelot Wind LLC2 MW39.8 km
New Bedford (MA) Plymouth4 MW40.5 km
Dennis Landfill5 MW41 km