← Back to map

Guse CSG

Waseca County, Minnesota · EIA plant ID 62195 · Operator: Terraform Arcadia
SolarSolar PhotovoltaicMISOBA: MISO
Nameplate1MWSummer 1 MW
Generators1in service
Net generation2GWh12 mo to Dec 2025
Capacity factor21%solar units, summer MW
Heat rate—thermal plants only
First online2018

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0100200300MWh2019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%20182019202020212022202320242025202620.9% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20180.28.3%—
20191.517.3%—
20201.820.3%—
20211.719.6%—
20221.314.7%—
20231.719.8%—
20241.820.3%—
20251.820.9%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
SO371Solar PhotovoltaicPV11Sep 2018Operating—coming soon

Owner / operator

Operator: Terraform Arcadia. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Terraform Arcadia100.0%1 MW

Nearby plants

Within 80 km.
Janesville5 MW2.8 km
Crane Creek Garden—4.3 km
Enter Solar1 MW5.5 km
Loon Garden1 MW12.1 km
Novel Winegar Partnership Solar CSG1 MW12.2 km
Everson Garden1 MW12.4 km