Lauderdale County, Mississippi · EIA plant ID 62163 · Operator: SR Meridian III
SolarSolar PhotovoltaicBA: SOCO
Nameplate53MWSummer 53 MW
Generators1in service
Net generation120GWh12 mo to Aug 2026
Capacity factor26%solar units, summer MW
Heat rate—thermal plants only
First online2019

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0510GWh2020202120222023202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%20192020202120222023202420252026202726.1% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20199.925.4%—
2020124.527.0%—
2021119.325.9%—
202212827.8%—
2023123.926.9%—
2024119.926.0%—
2025118.325.7%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
MRDIISolar PhotovoltaicPV52.552.5Dec 2019Operating—coming soon

Owner / operator

Operator: SR Meridian III. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
SR Meridian III100.0%53 MW

Nearby plants

Within 80 km.
Meridian II5 MW11.4 km
Meridian9 MW12 km
Sweatt42 MW25.8 km
Ratcliffe840 MW29.9 km
Kemper County372 MW38.6 km
WestRock Demopolis Mill47 MW53.8 km