← Back to map

Persimmon Creek Wind Farm 1, LLC

Woodward County, Oklahoma · EIA plant ID 61876 · Operator: Westar Energy Inc
WindOnshore Wind TurbineSPPBA: SWPP
Nameplate199MWSummer 199 MW
Generators1in service
Net generation864GWh12 mo to Aug 2026
Capacity factor50%wind units, summer MW
Heat rate—thermal plants only
First online2018

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0255075100GWh20192020202120222023202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), wind units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%2018202020222024202649.7% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2018279.148.0%—
2019925.853.2%—
2020905.251.9%—
2021820.147.1%—
2022832.947.9%—
2023827.747.6%—
2024876.150.2%—
2025825.847.5%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
PCWF1Onshore Wind TurbineWT198.6198.6Sep 2018Operating—ge 2.5-120

Owner / operator

Operator: Westar Energy Inc. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Westar Energy Inc100.0%199 MW

Nearby plants

Within 80 km.
Keenan II Renewable Energy Co LLC152 MW17 km
OU Spirit Wind Farm101 MW21.3 km
Great Western Wind Energy, LLC225 MW22.2 km
Mooreland305 MW31.3 km
Seiling Wind I199 MW32.6 km
Seiling Wind II99 MW32.6 km