← Back to map

Vale Solar Center

Malheur County, Oregon · EIA plant ID 61856 · Operator: Enerparc Inc.
SolarSolar PhotovoltaicBA: IPCO
Nameplate3MWSummer 3 MW
Generators1in service
Net generation6GWh12 mo to Dec 2025
Capacity factor23%solar units, summer MW
Heat rate—thermal plants only
First online2020

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0200400600800MWh20212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%202020212022202320242025202623.5% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20202.724.3%—
20215.922.5%—
20225.822.1%—
20235.721.7%—
20245.520.9%—
20256.223.5%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
VALESolar PhotovoltaicPV33Aug 2020Operating—coming soon

Owner / operator

Operator: Enerparc Inc.. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Enerparc Inc.100.0%3 MW

Nearby plants

Within 80 km.
Neal Hot Springs Geothermal Project33 MW15.1 km
Durbin Creek Windfarm (Burnt River)10 MW23.8 km
Benson Creek Windfarm (Burnt River)10 MW24.6 km
Grove Solar Center, LLC6 MW25.1 km
Vale Air Solar Center, LLC10 MW26.1 km
Willow Spring Windfarm (Burnt River)10 MW28.4 km