← Back to map

Robins Air Force Base Solar

Bibb County, Georgia · EIA plant ID 61648 · Operator: Georgia Power Co
SolarBatteriesSolar PhotovoltaicBA: SOCO
Nameplate256MWSummer 256 MW
Generators2in service
Net generation195GWh12 mo to Aug 2026
Capacity factor18%solar units, summer MW
Heat rate—thermal plants only
First online2021

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
01020GWh20222023202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%202120222023202420252026202717.8% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2021204.524.2%—
2022255.422.8%—
2023225.220.1%—
202419217.1%—
2025206.918.4%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Solar PhotovoltaicPV128128Apr 2021Operating—coming soon
2BatteriesBA128128Mar 2026Operating—coming soon

Owner / operator

Operator: Georgia Power Co. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Georgia Power Co100.0%256 MW

Nearby plants

Within 80 km.
Riverwood International Macon Mill69 MW10.1 km
Robins184 MW11.8 km
Twiggs Solar204 MW14.5 km
YKK USA Chestney2 MW15.4 km
ADS Renewable Energy-Wolf Creek LLC3 MW20 km
Bibb Williams2 MW20.5 km