← Back to map

Texon Hydroelectric Project

Hampden County, Massachusetts · EIA plant ID 61640 · Operator: Hitchcock Hydro, LLC
HydroConventional HydroelectricISONEBA: ISNE
Nameplate2MWSummer 2 MW
Generators1in service
Net generation4GWh12 mo to Dec 2025
Capacity factor30%hydro units, summer MW
Heat rate—thermal plants only
First online1982

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0200400600800MWh201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), hydro units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%2018202020222024202629.9% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20174.231.7%—
20186.347.7%—
20195.440.8%—
20204.232.0%—
20216.549.3%—
20223.627.3%—
20236.146.6%—
20244.332.7%—
20253.929.9%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Conventional HydroelectricHY1.51.5Jan 1982Operating—coming soon

Owner / operator

Operator: Hitchcock Hydro, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Hitchcock Hydro, LLC100.0%2 MW

Nearby plants

Within 80 km.
Holiday Hill Community Wind5 MW1.4 km
Indian River Hydro1 MW4 km
Russell (MA)3 MW6.3 km
Syncarpha Blandford Hybrid CSG9 MW6.6 km
International Paper Woronoco Mill3 MW7 km
CED Westfield Solar, LLC2 MW10 km