← Back to map

Montgomery County Solar

Montgomery County, Maryland · EIA plant ID 61608 · Operator: Montgomery County Solar
SolarSolar PhotovoltaicPJMBA: PJM
Nameplate2MWSummer 2 MW
Generators1in service
Net generation2GWh12 mo to Dec 2025
Capacity factor15%solar units, summer MW
Heat rate—thermal plants only
First online2018

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0100200300MWh2019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%5%10%15%20182019202020212022202320242025202614.6% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20181.313.2%—
20192.917.6%—
20202.917.1%—
20212.615.9%—
20222.716.0%—
20232.816.7%—
20242.716.3%—
20252.414.6%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Solar PhotovoltaicPV1.91.9Jun 2018Operating—coming soon

Owner / operator

Operator: Montgomery County Solar. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Montgomery County Solar100.0%2 MW

Nearby plants

Within 80 km.
NIST Solar4 MW2.3 km
Boyd Soccerplex1 MW7.9 km
MNCPPC Germantown Solar1 MW8.1 km
MO33 CSG2 MW13 km
Oaks Landfill CS 12 MW13.5 km
Oaks Landfill - ANEM2 MW13.5 km