Redbrook Community Solar 1
Plymouth County, Massachusetts · EIA plant ID 61007 · Operator: Redbrook Solar 1, LLC
Nameplate4MWSummer 4 MW
Generators1in service
Net generation1GWh12 mo to Dec 2025
Capacity factor4%solar units, summer MW
Heat rate—thermal plants only
First online2017
Monthly net generation
EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
Capacity factor by year
Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
| Year | Net GWh | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|
| 2017 | 0.5 | 6.1% | — |
| 2018 | 6.5 | 18.5% | — |
| 2019 | 6.4 | 18.3% | — |
| 2020 | 6.9 | 19.8% | — |
| 2021 | 7 | 19.9% | — |
| 2022 | 10.1 | 28.8% | — |
| 2023 | 9.9 | 28.3% | — |
| 2024 | 3.6 | 10.2% | — |
| 2025 | 1.4 | 4.1% | — |
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| REDBR | Solar Photovoltaic | PV | 4 | 4 | Oct 2017 | Operating | — | coming soon |
Owner / operator
Operator: Redbrook Solar 1, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
| Redbrook Solar 1, LLC | 100.0% | 4 MW |
Nearby plants
Within 80 km.
| Onset East Community Solar Facility | 1 MW | 4.6 km |
| Onset West Community Solar Facility | 1 MW | 4.6 km |
| Lepomis PV Energy LLC | 5 MW | 5.6 km |
| Future Generation Wind | 8 MW | 6.1 km |
| Cedarville CSG | 3 MW | 6.1 km |
| 665 Scenic Highway | 6 MW | 7.5 km |