← Back to map

Mt. Hope DPC Solar

Grant County, Wisconsin · EIA plant ID 60893 · Operator: SoCore Energy LLC
SolarSolar PhotovoltaicMISOBA: MISO
Nameplate1MWSummer 1 MW
Generators1in service
Net generation2GWh12 mo to Aug 2026
Capacity factor23%solar units, summer MW
Heat rate—thermal plants only
First online2017

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0100200MWh20162017201820192020202120222023202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%2018202020222024202623.4% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20160——
20171.921.3%—
2018222.8%—
20191.921.9%—
2020222.9%—
20211.921.7%—
20222.123.6%—
20232.123.9%—
20242.124.2%—
20252.123.5%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
PV1Solar PhotovoltaicPV11Jan 2017Operating—coming soon

Owner / operator

Operator: SoCore Energy LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
SoCore 2016 ProjectCo-W5 LLC100.0%1 MW

Nearby plants

Within 80 km.
Fennimore Solar3 MW13.8 km
Fennimore7 MW14.3 km
Cassville Solar50 MW25.8 km
McGregor2 MW28.4 km
Grant County300 MW30.4 km
Whitetail Wind Farm—31.9 km