← Back to map

Rail Trail

Berkshire County, Massachusetts · EIA plant ID 60492 · Operator: Altus Power America Management, LLC
SolarSolar PhotovoltaicISONEBA: ISNE
Nameplate2MWSummer 2 MW
Generators1in service
Net generation3GWh12 mo to Dec 2025
Capacity factor18%solar units, summer MW
Heat rate—thermal plants only
First online2016

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0100200300400MWh201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%5%10%15%20162018202020222024202617.6% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20162.218.4%—
20173.117.8%—
20182.816.2%—
20193.318.7%—
20203.319.1%—
20213.218.3%—
20223.218.4%—
20233.118.0%—
20243.318.9%—
20253.117.6%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
PV1Solar PhotovoltaicPV22May 2016Operating—coming soon

Owner / operator

Operator: Altus Power America Management, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Altus Power America Management, LLC100.0%2 MW

Nearby plants

Within 80 km.
Nolan1 MW0.5 km
Rising Paper3 MW2.3 km
Monument Valley3 MW2.8 km
Glendale Hydroelectric Project1 MW4.3 km
Kearsarge GB2 MW6.7 km
Truck Stop2 MW11.2 km