← Back to map

Montana Solar Facility

El Paso County, Texas · EIA plant ID 60300 · Operator: El Paso Electric Co
SolarSolar PhotovoltaicBA: EPE
Nameplate3MWSummer 3 MW
Generators1in service
Net generation6GWh12 mo to Dec 2025
Capacity factor21%solar units, summer MW
Heat rate—thermal plants only
First online2017

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
00.250.50.751GWh20182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%2018202020222024202620.9% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20174.927.5%—
20188.432.0%—
20198.431.8%—
20208.231.1%—
20217.930.1%—
20225.621.3%—
20233.914.8%—
20244.918.6%—
20255.520.9%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
IMPV1Solar PhotovoltaicPV33May 2017Operating—coming soon

Owner / operator

Operator: El Paso Electric Co. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
El Paso Electric Co100.0%3 MW

Nearby plants

Within 80 km.
Montana Power Station527 MW1.4 km
TJX 2021 DG El Paso DC2 MW11.3 km
Fort Bliss (DEA EPIC)2 MW14.7 km
Copper87 MW16 km
Phelps Dodge Refining20 MW17.2 km
Newman Solar11 MW26.9 km