Harpster Wind
Wyandot County, Ohio · EIA plant ID 60126 · Operator: OEE XVII, LLC
Nameplate2MWSummer 2 MW
Generators1in service
Net generation3GWh12 mo to Aug 2026
Capacity factor24%wind units, summer MW
Heat rate—thermal plants only
First online2016
The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.
Monthly net generation
EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
Capacity factor by year
Net MWh ÷ (summer MW × hours), wind units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
| Year | Net GWh | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|
| 2016 | 2.6 | 19.8% | — |
| 2017 | 3.7 | 27.9% | — |
| 2018 | 3.3 | 24.8% | — |
| 2019 | 3.4 | 26.1% | — |
| 2020 | 3.3 | 25.2% | — |
| 2021 | 3.2 | 24.4% | — |
| 2022 | 3.6 | 27.7% | — |
| 2023 | 2.9 | 22.2% | — |
| 2024 | 2 | 14.9% | — |
| 2025 | 3.1 | 23.9% | — |
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| H1 | Onshore Wind Turbine | WT | 1.5 | 1.5 | Jan 2016 | Operating | — | goldwind GW 87/1500 |
Owner / operator
Operator: OEE XVII, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
| Todd A.Stoller Living Trust | 95.0% | 1 MW |
| One Energy Capital LLC | 5.0% | 0 MW |
Nearby plants
Within 80 km.
| POET Biorefining - Marion, LLC | 8 MW | 12.3 km |
| Marion County Solar Project | 100 MW | 13 km |
| Whirlpool Corporation - Marion Wind Farm | 5 MW | 14.8 km |
| Wyandot Solar Farm | 10 MW | 19.4 km |
| Sycamore | 1 MW | 26 km |
| Prospect Municipal | 2 MW | 31 km |