← Back to map

Fort Benning Solar Facility

Chattahoochee County, Georgia · EIA plant ID 59862 · Operator: Georgia Power Co
SolarSolar PhotovoltaicBA: SOCO
Nameplate30MWSummer 30 MW
Generators1in service
Net generation55GWh12 mo to Aug 2026
Capacity factor21%solar units, summer MW
Heat rate—thermal plants only
First online2015

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0246GWh20162017201820192020202120222023202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%20162018202020222024202620.9% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20152.712.1%—
201660.723.0%—
20175621.3%—
201855.321.0%—
201953.320.3%—
202050.919.3%—
202148.118.3%—
20225320.2%—
202351.519.6%—
202451.519.5%—
20255621.3%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Solar PhotovoltaicPV3030Dec 2015Operating—coming soon

Owner / operator

Operator: Georgia Power Co. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Georgia Power Co100.0%30 MW

Nearby plants

Within 80 km.
North Highlands30 MW16.6 km
Oliver Dam60 MW16.7 km
Muscogee Public Works2 MW18.7 km
Mead Coated Board121 MW20.4 km
Lee County103 MW22 km
Goat Rock39 MW29.4 km