Pulaski County, Virginia · EIA plant ID 59845 · Operator: Ingenco Renewable Development, LLC
Nameplate5MWSummer 5 MW
Generators18in service
Net generation12GWh12 mo to Dec 2025
Capacity factor23%other units, summer MW
Heat rate11,346Btu/kWhfossil units, electric fuel, HHV
First online2013
Monthly net generation
EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
Capacity factor by year
Net MWh ÷ (summer MW × hours), other units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Annual data table
| Year | Net GWh | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|
| 2014 | 0 | — | — |
| 2015 | 16.9 | 32.8% | 10,786 |
| 2016 | 19.2 | 38.0% | 10,640 |
| 2017 | 18.8 | 37.3% | 10,675 |
| 2018 | 21 | 42.0% | 9,971 |
| 2019 | 19.4 | 39.4% | 10,829 |
| 2020 | 19.6 | 39.9% | 11,653 |
| 2021 | 17.7 | 36.2% | 11,538 |
| 2022 | 17.3 | 34.9% | 10,928 |
| 2023 | 13.7 | 27.4% | 13,175 |
| 2024 | 12.7 | 25.3% | 10,893 |
| 2025 | 11.6 | 23.3% | 11,346 |
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| E1 | Landfill Gas | IC | 0.3 | 0.3 | Sep 2013 | Operating | — | coming soon |
| E10 | Landfill Gas | IC | 0.3 | 0.3 | Sep 2013 | Operating | — | coming soon |
| E11 | Landfill Gas | IC | 0.3 | 0.3 | Sep 2013 | Operating | — | coming soon |
| E12 | Landfill Gas | IC | 0.3 | 0.3 | Sep 2013 | Operating | — | coming soon |
| E13 | Landfill Gas | IC | 0.3 | 0.3 | Sep 2013 | Operating | — | coming soon |
| E14 | Landfill Gas | IC | 0.3 | 0.3 | Sep 2013 | Operating | — | coming soon |
| E15 | Landfill Gas | IC | 0.3 | 0.3 | Sep 2013 | Operating | — | coming soon |
| E16 | Landfill Gas | IC | 0.3 | 0.3 | Sep 2013 | Operating | — | coming soon |
| E17 | Landfill Gas | IC | 0.3 | 0.3 | Sep 2013 | Operating | — | coming soon |
| E18 | Landfill Gas | IC | 0.3 | 0.3 | Sep 2013 | Operating | — | coming soon |
| E2 | Landfill Gas | IC | 0.3 | 0.3 | Sep 2013 | Operating | — | coming soon |
| E3 | Landfill Gas | IC | 0.3 | 0.3 | Sep 2013 | Operating | — | coming soon |
| E4 | Landfill Gas | IC | 0.3 | 0.3 | Sep 2013 | Operating | — | coming soon |
| E5 | Landfill Gas | IC | 0.3 | 0.3 | Sep 2013 | Operating | — | coming soon |
| E6 | Landfill Gas | IC | 0.3 | 0.3 | Sep 2013 | Operating | — | coming soon |
| E7 | Landfill Gas | IC | 0.3 | 0.3 | Sep 2013 | Operating | — | coming soon |
| E8 | Landfill Gas | IC | 0.3 | 0.3 | Sep 2013 | Operating | — | coming soon |
| E9 | Landfill Gas | IC | 0.3 | 0.3 | Sep 2013 | Operating | — | coming soon |
Owner / operator
Operator: Ingenco Renewable Development, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
| Ingenco Renewable Development, LLC | 100.0% | 5 MW |
Nearby plants
Within 80 km.
| Hecate Energy Pulaski 1 | — | 4.9 km |
| Radford Army Ammunition Plant | 18 MW | 13.8 km |
| Claytor | 75 MW | 15.7 km |
| Radford | 1 MW | 16.1 km |
| Celanese Acetate LLC | 27 MW | 18.8 km |
| Virginia Tech Power Plant | 6 MW | 25.2 km |