Campbell County Wind Farm

Campbell County, South Dakota · EIA plant ID 59655 · Operator: RWE Clean Energy
WindOnshore Wind TurbineSPPBA: SWPP
Nameplate94MWSummer 94 MW
Generators1in service
Net generation343GWh12 mo to Dec 2025
Capacity factor42%wind units, summer MW
Heat rate—thermal plants only
First online2015

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
010203040GWh2016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), wind units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%20162018202020222024202641.5% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20151.21.6%—
2016408.647.6%—
2017403.847.1%—
2018371.343.3%—
2019380.844.5%—
2020385.944.9%—
2021377.344.0%—
2022379.744.3%—
2023318.837.2%—
2024286.134.5%—
2025342.941.5%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
CCWF1Onshore Wind TurbineWT94.394.3Dec 2015Operating—ge 1.7-103

Owner / operator

Operator: RWE Clean Energy. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
RWE Clean Energy100.0%94 MW

Nearby plants

Within 80 km.
Emmons-Logan Wind, LLC200 MW71 km
Emmons-Logan Energy Storage—72.6 km
Badger Wind, LLC250 MW73.4 km