St. Lawrence County, New York · EIA plant ID 59623 · Operator: AES Distributed Energy
SolarSolar PhotovoltaicNYISOBA: NYIS
Nameplate2MWSummer 2 MW
Generators1in service
Net generation2GWh12 mo to Dec 2025
Capacity factor11%solar units, summer MW
Heat rate—thermal plants only
First online2014

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0100200300MWh20152016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%5%10%15%201420162018202020222024202611.1% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20140.12.6%—
20152.715.5%—
20162.715.3%—
20172.413.6%—
20182.313.0%—
20192.514.1%—
20201.910.6%—
2021211.6%—
20221.79.7%—
20231.79.9%—
20241.910.8%—
20251.911.1%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
CSPVSolar PhotovoltaicPV22Nov 2014Operating—coming soon

Owner / operator

Operator: AES Distributed Energy. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
AES Distributed Energy100.0%2 MW

Nearby plants

Within 80 km.
NY Potsdam 28 Hamilton St. Solar4 MW1.4 km
NY Lancaster Shisler Rd Site 2 Solar CSG5 MW1.4 km
Sugar Island4 MW3.9 km
Sissonville Hydro3 MW4.5 km
Hewittville Hydroelectric3 MW5.9 km
Unionville Hydro Project 2499 NY3 MW6 km