← Back to map

Life Technologies - Pleasanton

Alameda County, California · EIA plant ID 59279 · Operator: Bloom Energy
Natural gasOther Natural GasCAISOBA: CISO
Nameplate1MWSummer 1 MW
Generators1in service
Net generation8GWh12 mo to Dec 2025
Capacity factor95%gas/coal/oil units, summer MW
Heat rate7,171Btu/kWhfossil units, electric fuel, HHV
First online2013Runs as baseload

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
00.250.50.751GWh201420152016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), gas/coal/oil units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%25%50%75%201420162018202020222024202695.0% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
6,0007,0008,00020142016201820202022202420267,171 Btu/kWh · 12 mo
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20136.183.7%6,886
20147.888.7%7,382
20157.383.7%7,661
20167.585.9%7,503
20177.889.1%7,518
20187.586.1%7,574
20197.282.5%8,692
2020891.1%6,750
20218.495.5%7,081
2022891.2%7,129
2023890.9%6,892
20248.596.5%7,016
20258.395.0%7,171

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
LFT01Other Natural GasFC1.11Mar 2013Operating—coming soon

Owner / operator

Operator: Bloom Energy. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Life Technologies Corporation100.0%1 MW

Nearby plants

Within 80 km.
Thermo Fisher Pleasanton3 MW0.1 km
Kaiser Owens Dr. Fuel Cell1 MW6.2 km
NorCal FPV 1 (Pond 2)—6.3 km
NorCal FPV 1—6.3 km
Santa Rita Jail Fuel Cell1 MW8.4 km
Santa Rita Jail Hybrid3 MW8.4 km