Western Antelope Dry Ranch

Los Angeles County, California · EIA plant ID 58627 · Operator: AES Distributed Energy
SolarSolar PhotovoltaicCAISOBA: CISO
Nameplate10MWSummer 10 MW
Generators1in service
Net generation26GWh12 mo to Dec 2025
Capacity factor30%solar units, summer MW
Heat rate—thermal plants only
First online2016

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0123GWh201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%20162018202020222024202630.0% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20161.824.6%—
201727.131.0%—
201826.430.2%—
201926.630.4%—
20202629.6%—
202125.929.6%—
202226.830.6%—
202322.225.4%—
202421.824.8%—
202526.230.0%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
WADRSolar PhotovoltaicPV1010Dec 2016Operating—coming soon

Owner / operator

Operator: AES Distributed Energy. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
AES Distributed Energy100.0%10 MW

Nearby plants

Within 80 km.
TA-Acacia, LLC20 MW0.4 km
Antelope DSR 25 MW0.8 km
Western Antelope Blue Sky Ranch A20 MW0.9 km
Bayshore Solar C, LLC20 MW1 km
Lancaster Area Battery127 MW1.5 km
Luna Storage100 MW1.5 km