← Back to map

Western Michigan University Power Plant

Kalamazoo County, Michigan · EIA plant ID 58161 · Operator: Western Michigan University
Natural gasNatural Gas Fired Combined CycleNatural Gas Internal Combustion EngineMISOBA: MISO
Nameplate17MWSummer 15 MW
Generators6in service
Net generation81GWh12 mo to Dec 2025
Capacity factor61%gas/coal/oil units, summer MW
Heat rate4,979Btu/kWhfossil units, electric fuel, HHV
First online1997Runs as baseload

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
02.557.510GWh20122013201420152016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), gas/coal/oil units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%25%50%75%2012201420162018202020222024202661.2% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
2,5005,0007,50010,000201220142016201820202022202420264,979 Btu/kWh · 12 mo
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
201272.181.2%11,546
201372.481.9%11,665
201474.484.1%11,691
201569.178.1%11,688
201668.977.6%4,954
20177281.3%4,954
201870.279.3%4,954
201965.974.5%4,984
202057.765.0%5,014
20215849.2%5,037
202258.544.2%5,038
202371.353.9%5,164
202470.453.1%5,013
202580.961.2%4,979

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
EG-1Natural Gas Internal Combustion EngineIC0.80.8Mar 1999Operating—coming soon
EG-10Natural Gas Internal Combustion EngineIC2.52.5May 2021Operating—coming soon
EG-9Natural Gas Internal Combustion EngineIC2.52.5May 2021Operating—coming soon
GTG-7Natural Gas Fired Combined CycleCT54.2Aug 1997Operating—coming soon
GTG-8Natural Gas Fired Combined CycleCT54.2Aug 1997Operating—coming soon
STG-1Natural Gas Fired Combined CycleCA0.90.9Mar 1999Operating—coming soon

Owner / operator

Operator: Western Michigan University. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Western Michigan University100.0%17 MW

Nearby plants

Within 80 km.
Parkview Battery1 MW4.2 km
Western Michigan Solar Gardens1 MW4.3 km
Kalamazoo River Generating Station77 MW9.2 km
Liberty Solar Energy Center—14.3 km
Otsego Mill Power Plant21 MW21.6 km
Spring Creek Agri-Energy Center—31.5 km