← Back to map

Brookfield Tehachapi 1

Kern County, California · EIA plant ID 57962 · Operator: Coram California Development, L.P.
WindOnshore Wind TurbineCAISOBA: CISO
Nameplate102MWSummer 102 MW
Generators1in service
Net generation164GWh12 mo to Dec 2025
Capacity factor18%wind units, summer MW
Heat rate—thermal plants only
First online2012

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
-2002040GWh2013201420152016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), wind units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%2012201420162018202020222024202618.4% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2012184.424.6%—
2013277.731.1%—
2014280.831.4%—
2015237.426.6%—
2016286.432.0%—
2017254.828.5%—
2018275.130.8%—
201924727.6%—
2020250.628.0%—
2021274.430.7%—
2022261.129.2%—
2023220.424.7%—
2024276.930.9%—
2025164.518.4%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
BT1Onshore Wind TurbineWT102102Mar 2012Operating—vestas V90-3.0

Owner / operator

Operator: Coram California Development, L.P.. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Brookfield Renewable Energy Group100.0%102 MW

Nearby plants

Within 80 km.
Alta Wind Energy Center IV102 MW0.1 km
Alta Wind Energy Center V168 MW0.1 km
Alta Wind VIII150 MW2.1 km
Pinyon Pine II132 MW2.6 km
Windhub Solar B, LLC—2.6 km
SEPV Mojave West20 MW4.1 km