Solar Photovoltaic Project #48Retired

San Bernardino County, California · EIA plant ID 57900 · Operator: Southern California Edison Co
SolarCAISOBA: CISO

×5 MW solar retired since 2020 (latest Dec 2023)

Nameplate—MWSummer — MW
Generators0in service
Net generation—GWh12 mo
Capacity factor—no 923 generation in the last 12 months
Heat rate—thermal plants only
First online—

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
00.250.50.751GWh20162017201820192020202120222023

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%20162018202020222024

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2015922.4%—
2016715.8%—
20178.519.3%—
20187.917.9%—
2019613.7%—
20206.214.2%—
20214.911.3%—
202249.0%—
20230.71.7%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
S48ASolar PhotovoltaicPV0.50.5Feb 2015Retired Dec 2023—coming soon
S48BSolar PhotovoltaicPV0.50.5Feb 2015Retired Dec 2023—coming soon
S48CSolar PhotovoltaicPV0.50.5Feb 2015Retired Dec 2023—coming soon
S48DSolar PhotovoltaicPV0.50.5Feb 2015Retired Dec 2023—coming soon
S48ESolar PhotovoltaicPV0.50.5Feb 2015Retired Dec 2023—coming soon
S48FSolar PhotovoltaicPV0.50.5Feb 2015Retired Dec 2023—coming soon
S48GSolar PhotovoltaicPV0.50.5Feb 2015Retired Dec 2023—coming soon
S48HSolar PhotovoltaicPV0.50.5Feb 2015Retired Dec 2023—coming soon
S48ISolar PhotovoltaicPV0.50.5Feb 2015Retired Dec 2023—coming soon
S48JSolar PhotovoltaicPV0.50.5Feb 2015Retired Dec 2023—coming soon

Owner / operator

Operator: Southern California Edison Co. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).

Nearby plants

Within 80 km.
Solar Photovoltaic Project #07retired0.6 km
Solar Photovoltaic Project #05retired0.6 km
Solar Photovoltaic Project #16retired0.7 km
Solar Photovoltaic Project #13retired0.7 km
Mountainview Generating Station1,037 MW1.3 km
Solar Photovoltaic Project #11retired1.4 km