WindOnshore Wind TurbineBA: BPAT
Nameplate58MWSummer 58 MW
Generators1in service
Net generation158GWh12 mo to Dec 2025
Capacity factor31%wind units, summer MW
Heat rate—thermal plants only
First online2012

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
05101520GWh2013201420152016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), wind units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%2012201420162018202020222024202631.3% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
201260.228.5%—
2013132.626.3%—
2014164.432.6%—
201514628.9%—
2016177.235.0%—
2017171.133.9%—
2018159.631.6%—
2019162.632.2%—
2020183.436.3%—
2021175.134.7%—
2022162.832.3%—
2023149.429.6%—
2024167.433.1%—
202515831.3%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Onshore Wind TurbineWT57.657.6Aug 2012Operating—vestas V100-1.8

Owner / operator

Operator: Utah Associated Mun Power Sys. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Utah Associated Mun Power Sys100.0%58 MW

Nearby plants

Within 80 km.
Wolverine Creek65 MW9.1 km
Goshen Phase II125 MW12.6 km
IFP Peaking Plant18 MW13.4 km
Meadow Creek Project Company120 MW16.6 km
Cedar Creek Wind, LLC160 MW27.6 km