Bison 2 Wind Energy Center
Morton County, North Dakota · EIA plant ID 57800 · Operator: ALLETE, Inc.
Nameplate105MWSummer 105 MW
Generators1in service
Net generation270GWh12 mo to Dec 2025
Capacity factor29%wind units, summer MW
Heat rate—thermal plants only
First online2012
Monthly net generation
EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
Capacity factor by year
Net MWh ÷ (summer MW × hours), wind units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
| Year | Net GWh | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|
| 2012 | 4.4 | 5.7% | — |
| 2013 | 272.7 | 29.6% | — |
| 2014 | 324.1 | 35.2% | — |
| 2015 | 294.3 | 32.0% | — |
| 2016 | 328.8 | 35.6% | — |
| 2017 | 328.9 | 35.8% | — |
| 2018 | 276.2 | 30.0% | — |
| 2019 | 284.9 | 31.0% | — |
| 2020 | 316.3 | 34.3% | — |
| 2021 | 299.8 | 32.6% | — |
| 2022 | 323.8 | 35.2% | — |
| 2023 | 236.8 | 25.8% | — |
| 2024 | 218.7 | 23.7% | — |
| 2025 | 269.8 | 29.3% | — |
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| BISO2 | Onshore Wind Turbine | WT | 105 | 105 | Dec 2012 | Operating | — | siemens SWT-3.0-101 |
Owner / operator
Operator: ALLETE, Inc.. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
| ALLETE, Inc. | 100.0% | 105 MW |
Nearby plants
Within 80 km.
| Bison 3 Wind Energy Center | 105 MW | 0 km |
| Bison I Wind Energy Center | 82 MW | 0 km |
| Bison 4 Wind Energy Center | 205 MW | 0 km |
| Red Butte Wind | — | 11.1 km |
| Oliver Wind IV | 199 MW | 16.6 km |
| Glen Ullin Energy Center | 107 MW | 19.9 km |