← Back to map

RE Dillard 3 LLC

Sacramento County, California · EIA plant ID 57781 · Operator: GSRP
SolarSolar PhotovoltaicCAISOBA: BANC
Nameplate3MWSummer 3 MW
Generators1in service
Net generation6GWh12 mo to Dec 2025
Capacity factor22%solar units, summer MW
Heat rate—thermal plants only
First online2012

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
00.250.50.751GWh20122013201420152016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%2012201420162018202020222024202622.4% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20127.227.3%—
20137.629.0%—
20146.926.3%—
2015726.6%—
2016726.4%—
20176.825.9%—
20186.123.0%—
20196.223.6%—
20206.223.5%—
20216.324.0%—
20226.725.6%—
20236.223.5%—
20246.123.0%—
20255.922.4%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
DIL3Solar PhotovoltaicPV33Jan 2012Operating—coming soon

Owner / operator

Operator: GSRP. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
RE Dillard 3 LLC100.0%3 MW

Nearby plants

Within 80 km.
RE Dillard 4 LLC0 MW0 km
RE Dillard 2 LLC3 MW0.5 km
SloughHouse Solar, LLC50 MW0.7 km
RE Dillard 1 LLC3 MW0.8 km
Sacramento Soleil LLC1 MW1.9 km
Kiefer Landfill15 MW5.9 km