Montezuma Wind II

Solano County, California · EIA plant ID 57701 · Operator: NextEra Energy Montezuma Wind II, LLC
WindOnshore Wind TurbineCAISOBA: CISO
Nameplate78MWSummer 78 MW
Generators1in service
Net generation196GWh12 mo to Dec 2025
Capacity factor29%wind units, summer MW
Heat rate—thermal plants only
First online2012

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0102030GWh20122013201420152016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), wind units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%2012201420162018202020222024202628.6% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2012229.433.4%—
2013228.733.4%—
2014210.130.7%—
2015219.532.0%—
2016200.629.2%—
201719628.6%—
2018220.332.2%—
2019197.228.8%—
2020205.729.9%—
2021238.434.8%—
2022211.330.8%—
2023196.628.7%—
2024195.728.5%—
2025195.828.6%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Onshore Wind TurbineWT78.278.2Jan 2012Operating—siemens SWT-2.3-93

Owner / operator

Operator: NextEra Energy Montezuma Wind II, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
NextEra Energy Montezuma Wind II, LLC100.0%78 MW

Nearby plants

Within 80 km.
EDF Renewable Windfarm V Inc16 MW1 km
Shiloh I Wind Project150 MW2.5 km
High Winds LLC162 MW2.8 km
Shiloh IV Wind Project LLC103 MW3.7 km
Solano Wind301 MW4.6 km
FPL Energy Montezuma Winds LLC37 MW5.7 km