← Back to map

Allenwood

Lycoming County, Pennsylvania · EIA plant ID 57581 · Operator: EPP Renewable Energy
OtherLandfill GasPJMBA: PJM
Nameplate3MWSummer 3 MW
Generators2in service
Net generation10GWh12 mo to Dec 2025
Capacity factor34%other units, summer MW
Heat rate—thermal plants only
First online2012

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
00.511.52GWh2013201420152016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), other units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%50%100%2012201420162018202020222024202634.5% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20126.794.4%—
201326.795.2%—
201424.386.7%—
201525.189.5%—
201625.791.3%—
201724.687.8%—
201825.490.7%—
201924.286.3%—
202024.587.1%—
202123.583.8%—
202224.487.2%—
202322.580.4%—
202422.680.6%—
20259.734.5%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Landfill GasIC1.61.6Oct 2012Operating—coming soon
2Landfill GasIC1.61.6Oct 2012Operating—coming soon

Owner / operator

Operator: EPP Renewable Energy. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
EPP Renewable Energy100.0%3 MW

Nearby plants

Within 80 km.
Lycoming County3 MW0 km
Delaware Conrath Road Solar LLC—7.1 km
Hamilton Patriot Generation Plant870 MW7.4 km
PPL Martins Creek LLC Williamsportretired12.1 km
Muncy Creek Lime Bluff Road Solar—15.8 km
Lime Bluff 13 MW16.3 km