← Back to map

Robert O Schulz Solar Farm

Stanislaus County, California · EIA plant ID 57579 · Operator: South San Joaquin Irr District
SolarSolar PhotovoltaicCAISOBA: CISO
Nameplate2MWSummer 2 MW
Generators2in service
Net generation4GWh12 mo to Dec 2025
Capacity factor24%solar units, summer MW
Heat rate—thermal plants only
First online2008

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0200400MWh20102012201420162018202020222024

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%20102012201420162018202020222024202624.5% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2010326.3%—
20112.925.6%—
2012326.7%—
20133.126.9%—
20142.824.8%—
20152.925.8%—
20162.723.9%—
20172.925.2%—
20182.824.2%—
20192.723.8%—
20201.613.7%—
20212.219.0%—
20222.118.7%—
20231.714.9%—
20242.115.5%—
20253.925.0%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Solar PhotovoltaicPV0.91.1May 2008Operating—coming soon
2Solar PhotovoltaicPV0.70.7May 2009Operating—coming soon

Owner / operator

Operator: South San Joaquin Irr District. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
South San Joaquin Irr District100.0%2 MW

Nearby plants

Within 80 km.
Woodward Power Plant3 MW1.1 km
Frankenheimer Power Plant5 MW8.1 km
Da Silva Dairy1 MW10.6 km
Central Valley Ag Power2 MW15.4 km
Axium Modesto Solar25 MW16.5 km