← Back to map

Garland Canal Power Plant

Park County, Wyoming · EIA plant ID 57551 · Operator: Shoshone Irrigation District
HydroConventional HydroelectricBA: PACE
Nameplate3MWSummer 3 MW
Generators1in service
Net generation10GWh12 mo to Jul 2026
Capacity factor44%hydro units, summer MW
Heat rate—thermal plants only
First online1983

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
00.511.52GWh201020122014201620182020202220242026

Capacity factor by year

Net MWh ÷ (summer MW × hours), hydro units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%201020152020202543.5% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20109.742.6%—
20119.642.0%—
201210.244.6%—
20139.642.1%—
20149.240.4%—
20159.943.5%—
20169.642.0%—
20177.633.5%—
20189.240.4%—
20197.934.7%—
202010.144.4%—
20219.139.9%—
20221043.9%—
20239.240.5%—
20241043.9%—
20258.838.7%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
MAINConventional HydroelectricHY2.92.6Sep 1983Operating—coming soon

Owner / operator

Operator: Shoshone Irrigation District. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Shoshone Irrigation District100.0%3 MW

Nearby plants

Within 80 km.
Elk Basin Gasoline Plant1 MW28.3 km
Heart Mountain5 MW31.6 km
Spirit Mountain5 MW31.7 km
Buffalo Bill18 MW34.3 km
Shoshone (WY)3 MW35.3 km
Pryor Mountain Wind240 MW50.7 km