← Back to map

Barton Chapel Wind Farm

Jack County, Texas · EIA plant ID 57156 · Operator: Avangrid Renewables Inc
WindOnshore Wind TurbineERCOTBA: ERCO
Nameplate120MWSummer 120 MW
Generators1in service
Net generation127GWh12 mo to Dec 2025
Capacity factor12%wind units, summer MW
Heat rate—thermal plants only
First online2009

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
010203040GWh200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), wind units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%201020152020202512.1% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2009282.426.9%—
2010301.828.7%—
2011356.934.0%—
2012316.130.0%—
2013309.929.5%—
2014285.127.1%—
2015267.125.4%—
2016277.526.3%—
201725023.8%—
2018231.722.1%—
2019251.924.0%—
2020249.523.7%—
2021243.123.1%—
202224022.8%—
2023241.623.0%—
2024210.920.0%—
2025127.512.1%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
BCOnshore Wind TurbineWT120120Jan 2009Operating—gamesa G87-2.0

Owner / operator

Operator: Avangrid Renewables Inc. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Avangrid Renewables Inc100.0%120 MW

Nearby plants

Within 80 km.
Hecate Energy Longhorn Solar LLC650 MW6.2 km
O'Bannion Energy Storage—6.6 km
Senate Wind LLC150 MW12 km
Keechi Wind110 MW17.1 km
Graham635 MW25.8 km