White County, Indiana · EIA plant ID 57109 · Operator: Meadow Lake Wind Farm LLC
WindOnshore Wind TurbinePJMBA: PJM
Nameplate200MWSummer 200 MW
Generators1in service
Net generation432GWh12 mo to Dec 2025
Capacity factor25%wind units, summer MW
Heat rate—thermal plants only
First online2009

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0204060GWh20102012201420162018202020222024

Capacity factor by year

Net MWh ÷ (summer MW × hours), wind units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%201020152020202524.7% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2009133.630.3%—
201048827.9%—
201147227.0%—
2012466.926.6%—
2013477.627.3%—
2014495.428.3%—
201551229.3%—
201646826.7%—
2017445.525.5%—
2018446.825.5%—
2019475.427.2%—
2020454.825.9%—
2021413.423.6%—
2022460.726.3%—
202339922.8%—
2024442.825.2%—
2025431.724.7%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
GEN 1Onshore Wind TurbineWT199.7199.7Oct 2009Operating—vestas V82-1.65

Owner / operator

Operator: Meadow Lake Wind Farm LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Meadow Lake Wind Farm LLC100.0%200 MW

Nearby plants

Within 80 km.
Indiana Crossroads Wind Farm LLC302 MW6.8 km
Meadow Lake Wind Farm II LLC102 MW7.7 km
Meadow Lake Wind Farm III LLC104 MW7.8 km
Meadow Lake Wind Farm IV106 MW10 km
Meadow Lake Wind Farm V LLC100 MW12.2 km
Indiana Crossroads Solar Park200 MW13 km