← Back to map

Blue Canyon Windpower V LLC

Caddo County, Oklahoma · EIA plant ID 57108 · Operator: Blue Canyon Windpower V LLC
WindOnshore Wind TurbineSPPBA: SWPP
Nameplate99MWSummer 99 MW
Generators1in service
Net generation245GWh12 mo to Dec 2025
Capacity factor28%wind units, summer MW
Heat rate—thermal plants only
First online2009

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
010203040GWh20102012201420162018202020222024

Capacity factor by year

Net MWh ÷ (summer MW × hours), wind units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%201020152020202528.2% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20098237.5%—
2010337.438.9%—
2011388.644.8%—
2012382.544.0%—
2013376.543.4%—
2014393.245.3%—
2015339.339.1%—
2016365.242.0%—
2017371.142.8%—
2018362.241.8%—
2019363.441.9%—
202035540.8%—
2021290.333.5%—
2022291.133.6%—
202327231.4%—
2024262.830.2%—
2025244.728.2%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
GEN 1Onshore Wind TurbineWT9999Oct 2009Operating—ge 1.5 SLE

Owner / operator

Operator: Blue Canyon Windpower V LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Blue Canyon Windpower V LLC100.0%99 MW

Nearby plants

Within 80 km.
Blue Canyon Windpower74 MW11.8 km
Blue Canyon Windpower VI LLC100 MW13.9 km
Blue Canyon Windpower II151 MW14.8 km
Caddo Wind303 MW19.2 km
Pine Ridge3 MW21.3 km
Cyril5 MW22.2 km