← Back to map

Rugby Wind Power Project

Pierce County, North Dakota · EIA plant ID 57097 · Operator: Avangrid Renewables Inc
WindOnshore Wind TurbineMISOBA: MISO
Nameplate149MWSummer 149 MW
Generators1in service
Net generation348GWh12 mo to Dec 2025
Capacity factor27%wind units, summer MW
Heat rate—thermal plants only
First online2009

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
02040GWh20092012201420162018202020222024

Capacity factor by year

Net MWh ÷ (summer MW × hours), wind units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%201020152020202526.7% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
200900.0%—
2010324.124.8%—
2011395.730.3%—
2012405.331.0%—
2013383.829.4%—
2014434.233.3%—
2015366.728.1%—
2016404.530.9%—
2017428.632.8%—
2018406.731.2%—
2019393.230.1%—
2020363.127.7%—
2021411.331.5%—
2022429.432.9%—
2023333.225.5%—
2024335.425.6%—
2025348.126.7%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Onshore Wind TurbineWT149149Dec 2009Operating—suzlon S88-2100

Owner / operator

Operator: Avangrid Renewables Inc. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Avangrid Renewables Inc100.0%149 MW

Nearby plants

Within 80 km.
Border Winds Wind Farm150 MW57.6 km