Parker County, Texas · EIA plant ID 57020 · Operator: WM Renewable Energy LLC
Nameplate3MWSummer 3 MW
Generators2in service
Net generation19GWh12 mo to Dec 2025
Capacity factor67%other units, summer MW
Heat rate—thermal plants only
First online2010
Monthly net generation
EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
Capacity factor by year
Net MWh ÷ (summer MW × hours), other units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
| Year | Net GWh | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|
| 2010 | 22.9 | 65.0% | — |
| 2011 | 29.2 | 69.5% | — |
| 2012 | 31.1 | 73.7% | — |
| 2013 | 31 | 73.8% | — |
| 2014 | 27.4 | 65.1% | — |
| 2015 | 30.2 | 71.9% | — |
| 2016 | 36.9 | 87.6% | — |
| 2017 | 33 | 78.4% | — |
| 2018 | 29.5 | 70.2% | — |
| 2019 | 24.4 | 86.9% | — |
| 2020 | 24.2 | 86.0% | — |
| 2021 | 11.9 | 42.4% | — |
| 2022 | 15.1 | 54.0% | — |
| 2023 | 22 | 78.5% | — |
| 2024 | 15.7 | 55.9% | — |
| 2025 | 18.8 | 67.0% | — |
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| GEN1 | Landfill Gas | IC | 1.6 | 1.6 | Mar 2010 | Operating | — | coming soon |
| GEN2 | Landfill Gas | IC | 1.6 | 1.6 | Mar 2010 | Operating | — | coming soon |
| GEN3 | Landfill Gas | IC | 1.6 | 1.6 | Mar 2010 | Retired Oct 2017 | — | coming soon |
Owner / operator
Operator: WM Renewable Energy LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
| WM Renewable Energy LLC | 100.0% | 3 MW |
Nearby plants
Within 80 km.
| WAL3773 | 1 MW | 6.7 km |
| WAL4509 | 1 MW | 8.3 km |
| WAL940 | 1 MW | 10.2 km |
| OTHERTraditionClearfork | 1 MW | 12.2 km |
| WAL972 | 1 MW | 14.3 km |
| Gigawatt Solar | — | 20.5 km |