← Back to map

Hardin Hilltop Wind LLC

Greene County, Iowa · EIA plant ID 56860 · Operator: Hardin Holdco LLC
WindOnshore Wind TurbineMISOBA: MISO
Nameplate15MWSummer 15 MW
Generators1in service
Net generation31GWh12 mo to Dec 2025
Capacity factor24%wind units, summer MW
Heat rate—thermal plants only
First online2007

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
024GWh2007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), wind units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%201020152020202524.2% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20071416.2%—
200830.623.7%—
200933.926.3%—
201039.430.6%—
201147.136.6%—
201247.136.5%—
201349.238.2%—
20144736.5%—
201544.634.6%—
201645.635.3%—
201744.734.7%—
201840.931.8%—
201939.530.6%—
202043.733.9%—
202142.933.3%—
202238.830.1%—
202334.727.0%—
202432.425.1%—
202531.224.3%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Onshore Wind TurbineWT14.714.7May 2007Operating—suzlon S88-2100

Owner / operator

Operator: Hardin Holdco LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Hardin Holdco LLC100.0%15 MW

Nearby plants

Within 80 km.
Grand Junction2 MW5.9 km
Junction Hilltop Wind Farm8 MW8.1 km
Rippey Wind Farm50 MW13.5 km
Beaver Creek Wind340 MW16.8 km
Gowrie3 MW23.2 km
Ogden4 MW26.8 km