← Back to map

Brunswick Landfill Gas

Brunswick County, Virginia · EIA plant ID 56682 · Operator: Industrial Power Generating Company LLC
OtherLandfill GasPJMBA: PJM
Nameplate11MWSummer 11 MW
Generators35in service
Net generation44GWh12 mo to Dec 2025
Capacity factor45%other units, summer MW
Heat rate10,049Btu/kWhfossil units, electric fuel, HHV
First online2007

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0246GWh2007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), other units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%60%201020152020202544.7% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
6,0008,00010,00012,000201020152020202510,049 Btu/kWh · 12 mo
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20077.226.8%8,006
200835.433.4%7,929
20091211.9%10,871
201019.719.7%10,065
20117.37.3%10,324
201235.936.7%10,978
201330.631.7%11,730
201448.949.0%11,012
201555.656.2%10,724
201653.454.7%12,442
201753.554.9%10,872
201849.851.3%10,818
201946.548.6%11,293
202044.746.7%11,971
202141.543.9%12,231
20224345.5%11,578
202345.146.5%10,671
202443.444.7%10,715
202544.244.7%10,049

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
10Landfill GasIC0.30.3Oct 2007Operating—coming soon
11Landfill GasIC0.30.3Oct 2007Operating—coming soon
12Landfill GasIC0.30.3Oct 2007Operating—coming soon
13Landfill GasIC0.30.3Oct 2007Operating—coming soon
14Landfill GasIC0.30.3Oct 2007Operating—coming soon
15Landfill GasIC0.30.3Oct 2007Operating—coming soon
16Landfill GasIC0.30.3Oct 2007Operating—coming soon
17Landfill GasIC0.30.3Oct 2007Operating—coming soon
18Landfill GasIC0.30.3Oct 2007Operating—coming soon
19Landfill GasIC0.30.3Oct 2007Operating—coming soon
2Landfill GasIC0.30.3Oct 2007Operating—coming soon
20Landfill GasIC0.30.3Oct 2007Operating—coming soon
21Landfill GasIC0.30.3Oct 2007Operating—coming soon
22Landfill GasIC0.30.3Oct 2007Operating—coming soon
23Landfill GasIC0.30.3Oct 2007Operating—coming soon
24Landfill GasIC0.30.3Oct 2007Operating—coming soon
25Landfill GasIC0.30.3Oct 2007Operating—coming soon
26Landfill GasIC0.30.3Oct 2007Operating—coming soon
27Landfill GasIC0.30.3Oct 2007Operating—coming soon
28Landfill GasIC0.30.3Oct 2007Operating—coming soon
29Landfill GasIC0.30.3Oct 2007Operating—coming soon
3Landfill GasIC0.30.3Oct 2007Operating—coming soon
30Landfill GasIC0.30.3Oct 2007Operating—coming soon
31Landfill GasIC0.30.3Oct 2007Operating—coming soon
32Landfill GasIC0.30.3Oct 2007Operating—coming soon
33Landfill GasIC0.30.3Oct 2007Operating—coming soon
34Landfill GasIC0.30.3Oct 2007Operating—coming soon
35Landfill GasIC0.30.3Oct 2007Operating—coming soon
36Landfill GasIC0.30.3Oct 2007Operating—coming soon
4Landfill GasIC0.30.3Oct 2007Operating—coming soon
5Landfill GasIC0.30.3Oct 2007Operating—coming soon
6Landfill GasIC0.30.3Oct 2007Operating—coming soon
7Landfill GasIC0.30.3Oct 2007Operating—coming soon
8Landfill GasIC0.30.3Oct 2007Operating—coming soon
9Landfill GasIC0.30.3Oct 2007Operating—coming soon

Owner / operator

Operator: Industrial Power Generating Company LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Industrial Power Generating Company LLC100.0%11 MW

Nearby plants

Within 80 km.
Brunswick County Power Station1,472 MW8.6 km
Alberta Solar—12.4 km
Greensville County Power Station1,773 MW15.2 km
Fountain Creek Solar80 MW23.1 km
Emporia3 MW23.6 km
Meherrin Solar60 MW24.1 km