Peetz Table Wind Energy
Logan County, Colorado · EIA plant ID 56563 · Operator: FPL Peetz Table Wind Energy
Nameplate200MWSummer 200 MW
Generators1in service
Net generation674GWh12 mo to Dec 2025
Capacity factor39%wind units, summer MW
Heat rate—thermal plants only
First online2007
Monthly net generation
EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
Capacity factor by year
Net MWh ÷ (summer MW × hours), wind units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
| Year | Net GWh | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|
| 2007 | 220.7 | 37.8% | — |
| 2008 | 694.1 | 39.6% | — |
| 2009 | 640.1 | 36.6% | — |
| 2010 | 618.4 | 35.4% | — |
| 2011 | 656.7 | 37.6% | — |
| 2012 | 648.6 | 37.0% | — |
| 2013 | 667.1 | 38.2% | — |
| 2014 | 618.7 | 35.4% | — |
| 2015 | 545.2 | 31.2% | — |
| 2016 | 616.3 | 35.2% | — |
| 2017 | 603.9 | 34.6% | — |
| 2018 | 548.2 | 31.4% | — |
| 2019 | 508.4 | 29.1% | — |
| 2020 | 672.7 | 38.4% | — |
| 2021 | 623.7 | 35.7% | — |
| 2022 | 753.1 | 43.1% | — |
| 2023 | 653.2 | 37.4% | — |
| 2024 | 686.8 | 39.2% | — |
| 2025 | 673.9 | 38.6% | — |
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| GE | Onshore Wind Turbine | WT | 199.5 | 199.5 | Sep 2007 | Operating | — | ge 1.5 SLE |
Owner / operator
Operator: FPL Peetz Table Wind Energy. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
| FPL Peetz Table Wind Energy | 100.0% | 200 MW |
Nearby plants
Within 80 km.
| Logan Wind Energy | 201 MW | 15.7 km |
| Cedar Creek II | 248 MW | 29.5 km |
| Spring Canyon Expansion Wind Energy Ctr | 63 MW | 30.2 km |
| Kimball | 8 MW | 34.1 km |
| Kimball Wind | 30 MW | 38.8 km |
| Spring Canyon | 60 MW | 39.6 km |