Buffalo Mountain Energy CenterRetired
Anderson County, Tennessee · EIA plant ID 56493 · Operator: Invenergy Services LLC
×27 MW wind retired since 2020 (latest Dec 2024)
Nameplate—MWSummer — MW
Generators0in service
Net generation—GWh12 mo
Capacity factor—no 923 generation in the last 12 months
Heat rate—thermal plants only
First online—
Monthly net generation
EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
Capacity factor by year
Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
| Year | Net GWh | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|
| 2006 | 52 | 22.0% | — |
| 2007 | 47.7 | 20.2% | — |
| 2008 | 48.5 | 20.4% | — |
| 2009 | 51.4 | 21.7% | — |
| 2010 | 40.6 | 17.2% | — |
| 2011 | 53.1 | 22.5% | — |
| 2012 | 47.5 | 20.0% | — |
| 2013 | 46.7 | 19.8% | — |
| 2014 | 51.1 | 21.6% | — |
| 2015 | 45.8 | 19.4% | — |
| 2016 | 37.7 | 15.9% | — |
| 2017 | 43.3 | 18.3% | — |
| 2018 | 41 | 17.3% | — |
| 2019 | 38 | 16.1% | — |
| 2020 | 39.2 | 16.5% | — |
| 2021 | 28.2 | 11.9% | — |
| 2022 | 14.9 | 6.3% | — |
| 2023 | 16.2 | 6.9% | — |
| 2024 | 13.2 | 6.1% | — |
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| 4 | Onshore Wind Turbine | WT | 27 | 27 | Dec 2004 | Retired Dec 2024 | — | vestas V80-1.8 |
Owner / operator
Operator: Invenergy Services LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Nearby plants
Within 80 km.
| Bull Run | retired | 20.6 km |
| Norris Dam | 131 MW | 25.1 km |
| Melton Hill | 72 MW | 27.2 km |
| Chestnut Ridge Gas Recovery | 5 MW | 28.1 km |
| Kingston | 1,700 MW | 29.8 km |