Post Wind Farm LP

Borden County, Texas · EIA plant ID 56457 · Operator: FPL Energy Red Canyon LLC
WindOnshore Wind TurbineERCOTBA: ERCO
Nameplate84MWSummer 84 MW
Generators1in service
Net generation312GWh12 mo to Dec 2025
Capacity factor42%wind units, summer MW
Heat rate—thermal plants only
First online2006

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0102030GWh2007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), wind units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%201020152020202542.4% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2006202.636.5%—
2007287.739.1%—
2008330.444.8%—
2009280.738.1%—
2010295.940.2%—
2011312.642.5%—
2012300.340.7%—
2013300.440.8%—
2014311.442.3%—
2015277.937.8%—
2016294.639.9%—
201726936.6%—
2018334.745.5%—
2019340.246.2%—
202033345.1%—
2021196.126.7%—
2022329.444.8%—
2023311.742.4%—
2024314.842.7%—
2025311.842.4%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Onshore Wind TurbineWT8484Apr 2006Operating—ge 1.5 SLE

Owner / operator

Operator: FPL Energy Red Canyon LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
FPL Energy Red Canyon LLC100.0%84 MW

Nearby plants

Within 80 km.
Gopher Creek Wind Farm158 MW5.7 km
Fluvanna155 MW7.1 km
Brazos Wind Farm182 MW7.1 km
Lumina Solar Project487 MW22.3 km
TX13 Endurance Park Storage50 MW22.6 km
Juno Solar Project306 MW23.3 km