Buena Vista Energy LLC

Contra Costa County, California · EIA plant ID 56446 · Operator: Leeward Asset Management, LLC
WindOnshore Wind TurbineCAISOBA: CISO
Nameplate38MWSummer 38 MW
Generators1in service
Net generation96GWh12 mo to Dec 2025
Capacity factor29%wind units, summer MW
Heat rate—thermal plants only
First online2006

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
051015GWh2007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), wind units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%201020152020202528.9% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20060.31.1%—
2007106.932.1%—
2008100.830.2%—
20099829.4%—
201089.226.8%—
201195.228.6%—
20129829.3%—
2013102.830.9%—
201491.227.4%—
201510330.9%—
20169528.4%—
201786.426.0%—
201898.329.5%—
201987.926.4%—
202085.325.5%—
2021102.230.7%—
202293.228.0%—
202390.927.3%—
202489.626.9%—
202596.128.9%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Onshore Wind TurbineWT3838Dec 2006Operating—mitsubishi MWT-1000

Owner / operator

Operator: Leeward Asset Management, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Leeward Asset Management, LLC100.0%38 MW

Nearby plants

Within 80 km.
Vasco Winds78 MW4.7 km
Golden Hills North Wind Energy Center46 MW5.1 km
Summit Winds58 MW5.3 km
Mariposa Energy Project200 MW6 km
Altamont Gas Recovery6 MW6.4 km
Byron Highway Solar5 MW6.4 km